Summary
Parks and Rec will host seven pop-ups at the AMP construction site to let the public follow the planning and construction. The commission will staff a booth, starting April 12.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 6, 2026.
Impact analysis
Apparent low bids of $4,546,001.96, roughly $100K under the $6 million budget from cell tower funds.
Residents curious about the amphitheater project who want to watch and comment on construction progress.
Mentions & discussions (3)
City Council - Aug 6, 2026
Council created a dedicated amphitheater fund and put $125,000 into it for the rest of 2026 to track revenues and costs of running the venue.
Urban Forestry Commission (Regular) - Mar 9, 2026
Parks and Rec will host seven pop-ups at the AMP construction site to let the public follow the planning and construction. The commission will staff a booth, starting April 12.
City Council - Jan 22, 2026
Fourteen contractors bid on the amphitheater project, and the apparent low bids total about $4.55 million — under the architect's estimate and about $100K under the $6 million the city set aside from cell tower funds. Competition was strong, which kept prices down.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Stow
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.