The city locked in $3.6 million in federal CMAQ money for the roundabout at Fishcreek and Stow Roads. That's one of the area's busiest and trickiest intersections.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed May 14, 2026.
Impact analysis
$3.6 million in federal grant money coming into the city for the roundabout.
Drivers who use the Fishcreek/Stow intersection get a safer, smoother crossing.
Mentions & discussions (3)
City Council - May 14, 2026
Council hired EMH&T to design a roundabout at Fishcreek Road and Stow Road — a busy intersection residents know well.
City Council - Feb 26, 2026
The city locked in $3.6 million in federal CMAQ money for the roundabout at Fishcreek and Stow Roads. That's one of the area's busiest and trickiest intersections.
Roads and Safety Committee - Feb 26, 2026
The city is accepting $3.6 million in federal CMAQ funds to build a roundabout at Fishcreek and Stow Roads. Right-of-way work could start as early as 2028, with construction in 2030.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Stow
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.