Summary
The city is replacing the aging Liberty Road waterline and culvert, an $866,750 project in the 2026 water capital budget.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Feb 26, 2026.
Impact analysis
$866,750 from the 2026 Water Capital Fund.
Residents and businesses along Liberty Road get more reliable water service and drainage.
Mentions & discussions (2)
City Council - Feb 26, 2026
The city is replacing the aging Liberty Road waterline and culvert, an $866,750 project in the 2026 water capital budget.
Public Improvements Committee - Feb 26, 2026
The city is bundling a waterline replacement and culvert work on Liberty Road into one contract to get a better price — roughly $867,000 from the water capital fund.