Mangini Ranch Trails Project Construction Package

Stow

Summary

Four resolutions would have awarded a $2.77 million construction contract to Consolidated Engineering, denied a bid protest from Dutch Contracting, and hired Kimley-Horn and Pinnacle for construction support — a major new trails investment. None advanced because the meeting was canceled.

At a glance

Total mentions
1
Last 30 days
0

Last discussed May 28, 2026.

Impact analysis

💰Financial impact

About $3.18 million total, including contract, contingency, and construction management costs, from the Folsom Plan Area Capital Fund.

✅Who benefits

Trail users and neighborhoods near the Mangini Ranch area who would gain new or improved trails.

⚠️Who could be affected

Dutch Contracting Inc., whose bid protest would have been denied.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Stow

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.